Products & Services Submit a ticket My Tickets
Selamat datang
Masuk  Mendaftar

[COMPLETED] Announcement - Scheduled Power Maintenance At KL Data Center.

Date: 12th Jun 2021

Time: 8:00 AM MYT

Maintenance Update:
The Second Phase of Scheduled Power Maintenance has been completed. 


==============

Date: 22nd May 2021

Time: 8:00 AM MYT

Maintenance Update:
The First Phase of Scheduled Power Maintenance has been completed. 


==============

Dear Valued Customers,

 

Maintenance 1:

Planned Start Date: 22nd May 2021, 12.01 AM MYT
Planned End Date: 22nd May 2021, 8.00 AM MYT


Maintenance 2:

Planned Start Date: 12th Jun 2021, 12.01 AM MYT
Planned End Date: 12th Jun 2021, 8.00 AM MYT


Maintenance Detail:

Please be informed that there will be a power shutdown in our KL data center by our upstream provider to carry out major maintenance and replace faulty internal components.


Our team will perform switching over redundant power before actual maintenance and affected Dedicated Server/Colo clients will be notify privately.

 

Maintenance Affects:

During this maintenance window, all servers under KL data center shall continue operate via redundant power with remain service unaffected.

 

Best Regards,

 

Support Team

......................................

Technical Support Department